Latest news on the proposed Triangle Quarry Expansion at RDU

Entry 4: May 2019 – Engineering and Mine Planning

Wake Stone is now in the process of compiling and analyzing the data gathered from the exploratory drilling. The data will be entered into modeling and design software to begin the task of developing a potential mining plan and calculating the volume of material that can be excavated from the mine expansion. This part of the process is critical in determining the viability of the expansion, and is expected to take several weeks. During this time, there will likely be very little activity on the property. However, it is possible that additional testing of the site could be required as the data is analyzed and potential mining plans are discussed and reviewed.